A’s stadium groundbreaking Las Vegas signals fast start on Las Vegas Strip ballpark as construction advances

On June 23, 2025, the Oakland Athletics broke ground on a $1.75 billion, domed, 33,000‑seat “Armadillo” ballpark on the Las Vegas Strip; the stadium targets completion by January 2028 ahead of the A’s MLB debut in Nevada.

Key takeaways

Groundbreaking ceremony and who was there

Mounds of dirt, construction vehicles and the marked spot for home plate provided the backdrop as owners, officials and fans gathered for the groundbreaking. Team owner John Fisher told the crowd,

“We are Vegas’ team.”

MLB Commissioner Rob Manfred praised Las Vegas as a strong market, citing tourism and the success of other pro teams (A’s stadium groundbreaking Las Vegas, June 23, 2025 (ceremony)).

Also attending were Nevada Governor Joe Lombardo, former A’s stars Rollie Fingers and Dave Stewart, Little Leaguers, and Las Vegas Convention and Visitors Authority CEO Steve Hill. The ceremony was emceed by A’s broadcaster Dallas Braden (Las Vegas Sports Biz).

Design and features: an “Armadillo” on the Strip

The stadium is being designed by Danish firm BIG (Bjarke Ingels Group) with HNTB, Thornton Tomasetti and Henderson Engineers. The form — nicknamed the “Armadillo” — is five overlapping arched volumes clad in square metal panels and wedge shapes meant to evoke baseball pennants (Dezeen’s coverage of the BIG design).

Key design features include:

  • A domed roof and a domed lounge inside the ballpark.
  • The world’s largest cable‑net glass wall at the entrance.
  • Seating with 84% of seats located between the foul poles to keep fans close to play (ESPN).

Renders released in 2024 have guided public and lender briefings. The stadium footprint sits on nine acres of Bally’s 35‑acre site after the Tropicana hotel was demolished in October 2024 (New Las Vegas Stadium; Dezeen’s coverage of the BIG design).

Funding, approvals and legal framework

State lawmakers passed legislation (SB1) in June 2025 to secure public participation. Nevada and Clark County agreed to provide up to $380 million in public funds; the A’s plan to use $350 million of that total. The Las Vegas Stadium Authority finalized lease, non‑relocation and development agreements in December 2024, including a 30‑year rent‑free lease option that allows the team to buy and maintain the facility under agreed terms (ESPN; New Las Vegas Stadium).

Investigative note: Public funding and long‑term deals like the lease option have prompted debate over cost, oversight and contingency planning. Local reporting has flagged the need for clear auditing and plans should costs rise or timelines slip (Las Vegas Sports Biz).

Construction progress and schedule

Construction advanced quickly in late June 2025: the first deck pour is visible in the outfield, crews poured the second‑level concourse from the third‑base foul pole toward the first‑base line, and about half of the ballpark’s decks had been poured. Builders reported roof buttresses staging with the fifth of six due at month’s end and the sixth scheduled for spring 2026 (ESPN project briefings).

Timetable highlights from builders and project managers:

  • Steel work in the bowl: planned to begin March 2026.
  • Roof steel: expected to start appearing in June 2026; frame to take shape in summer and early fall 2026.
  • Interior systems: escalators and key systems to be staged on site in the coming weeks.

The general contractor is a McCarthy‑Mortenson joint venture, which previously worked on Allegiant Stadium for the Raiders (Las Vegas Sports Biz).

Team transition, temporary homes and fan ties

The A’s left Oakland after the 2024 season. From 2025 through at least 2027 they will play at a Triple‑A park in West Sacramento while the Las Vegas ballpark is built. The team plans visible ties to both cities during the transition; sleeve patches sponsored by the Las Vegas Convention and Visitors Authority will reference the team’s Bay Area history (ESPN).

Earlier site options included a west‑side Strip location near the former Wild Wild West property. The move to the Tropicana/Bally’s site was finalized after land and development negotiations and city planning approvals (Las Vegas Sports Biz; New Las Vegas Stadium).

Watch points and challenges

Project leaders say schedule and budget are on track, but analysts warn of two main risks: staying within the $1.75 billion budget and managing traffic and logistics on a busy stretch of the Strip. Future phases, including a casino, hotel and a 3,005‑room Bally’s resort, are planned to finish by 2030 and will require careful staging (Las Vegas Sports Biz).

Live tracking

Fans and reporters can follow progress through the A’s live construction cam and project pages: A’s construction cam and the MLB construction cam. These feeds provide photo updates, time‑lapses and project summaries.

Implications for Los Angeles, California

Economic impact: Los Angeles is a major feeder market for Las Vegas. The Strip ballpark is likely to draw more day and weekend visitors from L.A., increasing hotel bookings, flights and bus traffic. Travel agencies, airlines and tour operators could see higher demand for sports packages (ESPN).

Political consequences: The use of up to $350–$380 million in public funds will be watched by California officials and taxpayers. The project’s lease arrangements and oversight provisions may influence future stadium debates in Southern California (ESPN; New Las Vegas Stadium).

Social and cultural effects: The A’s in Las Vegas add MLB to an entertainment hub already home to the Raiders and Golden Knights. Southern California fans gain a closer neutral site for games, while broadcasters and advertisers may adapt regional rights and coverage plans.

Practical tip: Southern California fans should begin travel planning for 2028—advance bookings and packages will appear as the opening approaches. Local businesses may pursue partnerships with Vegas operators for events, travel and promotions.

Reporting and sources